The PMI Project includes the creation of a state-of-the-art Operational Center meant to host the heart of INAMET’s meteorological ecosystem.

In order to do so, the decision was taken to renovate an existing building, adjacent to INAMET’s headquarters: the "Georiscos Building”, former training center. 

The first phase of the work, which concerned demolition and structural work, was delivered in December 2019. 

On June 10th, 2020 the second phase of work was successfully inspected and accepted by INAMET’s representatives, leaving only 4 spaces (showers, kitchen, dining hall and shelter of the future generator) to be inspected separately. 

The server room, the calibration and maintenance workshop, the forecasting room and other offices are now at a finishing stage and almost ready to receive IT equipment and other furniture.